Municipal Roadway Marking Project
Municipal Roadway Pavement Markings in Gloversville, NY
Gloversville, New York
Capital Surface Maintenance completed various roadway pavement markings in the City of Gloversville, New York, for Jointa Lime Company, part of D.A. Collins. The work included field coordination with city officials, active-roadway striping and two mobilizations due to weather.
Request an Estimate →
Project Scope
Work Performed
Project Overview
Capital Surface Maintenance completed roadway pavement-marking work throughout portions of the City of Gloversville for Jointa Lime Company, part of D.A. Collins. The project involved multiple types of traffic and pedestrian markings on newly paved city streets.
The work required close coordination between CSM, the paving contractor and city representatives so the finished markings matched the intended roadway layout and could be installed safely in an active urban environment.
Field Coordination With City Officials
Before striping began, CSM met with City of Gloversville officials in the field to verbally review the required layout. This allowed the marking locations and roadway details to be confirmed directly on site before paint was applied.
Field coordination was especially important at intersections and other areas where crosswalks, arrows, lane lines and traffic movements needed to work together as one complete layout.
Roadway Markings in an Active City Environment
The project included a variety of roadway markings, including crosswalks, lane lines, directional arrows, intersection markings and other traffic-control pavement markings visible throughout the completed corridor.
Jointa Lime provided traffic control for the work areas, allowing the CSM crew to concentrate on layout and application while operating around live streets, intersections, pedestrians and surrounding properties.
Two Mobilizations Due to Weather
The roadway-marking scope was completed over two mobilizations because weather conditions prevented the entire project from being completed during the initial visit.
Returning for a second mobilization allowed the remaining markings to be installed under suitable conditions while maintaining the quality and consistency required across the project.
Project Results
The completed work provided clearly defined vehicle lanes, pedestrian crossings, directional guidance and intersection markings across the newly paved roadway areas.
The combination of contractor coordination, direct communication with city officials and flexible scheduling allowed the project to move from layout review through final pavement markings despite changing weather conditions.